3. Lunar Orbit (Duration 59:30) 75:54 - 135:24 GET LOI Day (Duration 25:00) 69:00 - 94:00 (a) LOI1 (b) Photos of targets of opportunity (c) LOI2 (d) Post LOI2 LM entry and inspection. S-Band/UHF B Voice tests will be conducted. (e) Post LOI2 Pseudo landmark tracking (one set of sightings) (See Table 1-4) (f) Rest period of 9 hours DOI and EVA Day (Duration 28:00) 94:00 - 122:00 GET (a) Docked LM activation and checkout (b) Docked landing site landmark sighting (one set of sightings) (See Table 1-3) (c) Undocking and separation (d) DOI thru landing (See Figure 1-3 Powered Descent) (e) LM post touchdown and simulated liftoff (f) Rest period (LM) of 4 hours (g) CSM plane change (h) Rest period (CSM) of 4 hours (i) EVA prep (j) EVA for 2 hours 40 minutes (k) Post EVA (1) Rest period (LM) 4 hours 40 minutes (m) Rest period (CSM) 4 hours 50 minutes Ascent and TEI Day (Duration 25:00) 122:00 - 147:00 GET (a) LM Lift-Off and Insertion (b) LM active rendezvous CSI PC CDH TPI Braking 1 - 2