CHAPTER  18  DAY  IN  THE  LIFE:  RISKY  AND  REWARDING  SPACEWALKS—SPACE  SHUTTLE  MISSION  STS-120/ISS-10A  310  For  these  reasons,  the  STS-120  mission  was  initially  planned  with  three  spacewalks  to  be  performed  by  crew  members  coming  up  in  the  shuttle  (Figure  4).  n  EVA  1.  The  first  EVA  was  required  to  disconnect  and  prepare  Node  2  so  it  could  be  robotically  unberthed  from  the  shuttle  cargo  bay  using  the  Space  Station  Robotic  Manipulator  System.  Also,  the  first  of  the  truss  element  P6  connections  were  to  be  demated  to  allow  for  its  later  release  from  the  central  truss  element  Z1.  Shuttle  astronauts  Scott  Parazynski  and  Doug  Wheelock  (nickname  “Wheels”)  were  trained  to  perform  this  EVA.  n  EVA  2.  The  second  EVA  was  needed  to  release  the  remaining  connections  and  bolts  for  a  final  disconnect  of  P6  from  Z1.  This  EVA  was  also  needed  to  install  critical  exterior  parts  onto  the  outside  of  Node  2  before  the  operations  in  the  stage  and  next  shuttle  missions.  Parazynski  and  Dan  Tani  were  trained  to  perform  this  EVA.  Between  EVAs  2  and  3,  extensive  robotic  operations  were  needed  to  move  the  P6  segment  close  to  its  final  location  on  the  P5  truss.  n  EVA  3.  The  third  EVA  was  needed  to  align,  bolt,  and  connect  up  P6  as  well  as  ready  a  radiator  for  deploy.  At  the  end  of  the  third  EVA,  while  the  EVA  crew  was  still  outside,  Mission  Control  Center-  Houston  would  start  deploying  the  radiator  and  P6  solar  arrays  2B  and  4B  to  begin  generating  power  for  ISS  use.  Shuttle  astronauts  Parazynski  and  Wheelock  were  trained  to  perform  this  EVA.  Several  secondary  objectives  were  included  with  the  three  EVAs.  One  task  was  to  remove  a  failed  antenna  called  the  S-band  Antenna  Support  Assembly,  which  weighed  103  kg  (228  lbs),  from  the  ISS  and  install  the  antenna  in  the  shuttle  cargo  bay  for  return  to  the  ground.  The  crew  also  took  a  new  spare  power  distribution  unit  called  a  Main  Bus  Switching  Unit,  which  is  238  kg  (525  lbs),  out  of  the  cargo  bay  and  placed  it  near  the  ISS  airlock  to  be  used  in  case  of  future  failures  of  this  type  of  unit.  These  operations  and  other  tasks  were  built  in  as  part  of  the  three  EVAs.  Originally,  three  other  ISS  EVAs  were  planned  after  the  STS-120  mission.  These  EVAs  were  needed  for  the  Node  2  move  to  its  final  location  on  the  forward  end  of  the  laboratory.  The  ISS  crew  had  been  training  for  these  “stage”  (i.e.,  shuttle  not  present)  EVAs.  See  the  Introduction  for  more  details  about  stage  EVAs.  Last-minute  Spacewalks  Added  to  the  Mission  Preflight  After  the  STS-120  mission  was  initially  planned,  the  shuttle  orbiters  were  changed  from  Atlantis  to  Discovery  due  to  a  delay  in  preparing  Atlantis  for  flight.  Discovery  had  been  outfitted  with  the  capability  to  draw  power  from  the  ISS  after  docking,  thus  the  mission  could  be  extended  and  the  number  of  EVAs  to  be  performed  during  the  mission  could  be  increased.  EVAs  during  shuttle  docked  mission  were  advantageous  because  the  combined  number  of  crew  members  on  board  would  be  10  (seven  shuttle,  three  ISS)  therefore,  more  crew  hours  would  be  available  to  get  the  spacewalkers  ready.  The  same  strategy  is  discussed  in  Chapter  4  with  respect  to  STS-130/ISS-20A.  As  a  result,  in  the  spring  of  2007,  a  pre-planned  stage  EVA  by  the  ISS  crew  was  moved  into  the  shuttle  docked  time  frame  to  bring  the  total  number  of  EVAs  during  the  mission  to  four.  Two  already-trained  ISS  crew  members  (Peggy  Whitson  and  Yuri  Malenchenko)  would  conduct  this  EVA.  They  would  perform  the  EVA  while  the  shuttle  was  present  instead  of  after  the  shuttle  departed.  The  team  knew  that  if  high-priority  EVA  tasks  went  long  or  new  tasks  were  required  during  the  shuttle  docked  time  frame,  the  fourth  planned  spacewalk  could  be  deferred  until  after  shuttle  departure.  Whitson  and  Malenchenko,  along  with  the  required  tools,  would  still  be  on  board.  The  main  purpose  of  this  EVA  was  to  get  a  step  closer  to  the  Columbus  module  mission  by  prepping  for  a  robotic  transfer  of  Pressurized  Mating  Adapter  2  to  Node  2  and  the  eventual  relocation  of  Node  2.  The  EVA  crew  would  be  demating  connectors  between  the  Pressurized  Mating  Adapter  and  the  Laboratory,  and  removing  a  cover  from  Node  2.  After  this  change,  and  about  a  month  prior  to  the  flight,  another  spacewalk  was  developed  and  added  to  the  mission  in  unusually  quick  fashion.  This  EVA  was  to  be  performed  by  Parazynski  and  Wheelock  to  test  some  material  that  could  repair  the  Space  Shuttle  orbiter  tiles,  if  damaged.  Ever  
Purchased by unknown, nofirst nolast From: Scampersandbox (scampersandbox.tizrapublisher.com)
 
            




















































































































































































































































































































































































































































