CHAPTER  18  DAY  IN  THE  LIFE:  RISKY  AND  REWARDING  SPACEWALKS—SPACE  SHUTTLE  MISSION  STS-120/ISS-10A  324  A  set  of  “overgloves”  was  planned  into  the  EVA  to  provide  for  this  sort  of  protection.  Overgloves  were  mittens  that  fit  over  the  index  finger  and  thumb  and  covered  the  most-used  glove  areas.  They  were  somewhat  loose,  thereby  reducing  the  overall  dexterity  of  the  crew  member’s  hands  even  more  than  the  spacesuit  gloves.  The  team  members  expressed  many  concerns  about  using  overgloves  when  doing  fine  detailed  EVA  work—  they  didn’t  want  Parazynski  unable  to  perform  the  repair,  snagging  the  overglove,  or  having  hand  fatigue.  It  was  agreed  that  both  Parazynski  and  Wheelock  would  wear  these  gloves,  but  when  Parazynski  got  on  the  tip  of  the  boom,  he  would  remove  his  overgloves  to  perform  the  repair.  Also  on  EVA  3,  Parazynski’s  spacesuit  exhibited  increasing  temperatures  due  to  a  theorized  failure  of  his  sublimator  (the  component  that  rejects  heat).  The  team  declared  his  primary  suit  “no-go”  for  use  on  this  upcoming  EVA.  The  crew  had  to  spend  extra  time  to  size  a  different  spare  suit  to  fit  him.  9.  Lack  of  Time  To  pull  off  this  kind  of  repair  spacewalk  could  take  weeks  of  preparation  in  various  ground  facilities  however,  only  a  handful  of  days  remained  before  the  shuttle  would  run  out  of  consumables  and  have  to  depart.  Even  simple  EVAs  are  usually  trained  in  the  Neutral  Buoyancy  Laboratory  several  times  before  attempted  in  space.  With  so  little  time,  a  lot  of  “gut  feel”  from  engineers,  flight  controllers,  and  experienced  crew  would  have  to  be  used  to  assess  robotic  motions  and  unknown  array  dynamics  during  the  repair.  Unfortunately,  the  same  people  who  had  worked  so  hard  (i.e.,  electrical  power  experts,  EVA  teams),  day  and  night,  to  come  up  with  the  SARJ  EVA  had  to  now  work  the  solar  array  issue  day  and  night  until  it  was  fixed.  The  array  snag  occurred  on  Tuesday,  October  30,  after  EVA  3.  On  Wednesday,  the  team  changed  direction,  completely  dropping  all  work  on  the  SARJ  and  instead  working  exclusively  on  the  repair  EVA.  Highly  optimistic  thinking  put  the  repair  EVA  on  Friday,  with  a  second  EVA  possible  before  undocking.  Everyone  felt  the  pressure  to  perform  a  successful  repair  before  the  shuttle  and  its  boom  departed.  Flight  Day  10  (Thursday,  November  1)  As  Friday  approached,  flight  controllers  worked  around  the  clock  (many  working  12  hours  or  more  at  a  time),  and  things  were  coming  together  the  night  before  the  spacewalk.  Almost.  The  team  struggled  to  get  the  final  procedures  on  board,  the  console  positions  in  mission  control  were  not  feeling  ready,  and  the  team  working  the  repair  EVA  details  was  exhausted.  The  flight  directors  involved  recognized  these  clues  as  “links  in  the  error  chain”  building  up.  Accident  investigations  often  point  at  links  in  the  error  chain  where  a  series  of  events  led  to  the  accident—if  any  one  event  had  been  recognized  and  stopped,  the  accident  could  have  been  prevented.  In  this  case,  the  team  was  not  meeting  all  of  the  deadlines,  and  people  were  heads-down  writing  the  details  to  the  point  of  not  looking  ahead  to  keep  important  big-picture  issues  in  mind.  Flight  controllers  might  have  pulled  off  the  EVA  that  Friday,  but  that  sick  feeling  that  everything  was  not  under  control  meant  an  error  chain  was  perhaps  developing.  The  team  needed  one  more  day.  The  flight  directors  and  program  management  agreed  to  move  the  EVA  from  Friday  to  Saturday.  This  meant  the  array  had  to  be  repaired  on  a  single  EVA—no  falling  back  on  a  second  EVA  since  there  would  not  be  time  for  a  follow-  on  EVA  before  the  shuttle  would  have  to  undock  with  its  remaining  consumables  to  make  it  home.  Flight  Day  11  (Friday,  November  2)  With  the  EVA  now  scheduled  for  Saturday,  the  final  conferences  were  conducted  on  Friday  with  the  crew  to  discuss  the  repair  details  and  robotics.  EVA  crew  members  had  procedures  on  board  that  they  printed  out  and  taped  to  their  cuff  checklist  so  that  Parazynski  would  have  a  graphic  representation  of  where  he  would  install  the  cufflinks  (Figures  17-19).  Tani  and  Wilson  would  be  the  station  robotics  crew  members,  and  they  had  procedures  on  board  and  were  feeling  ready.  The  general  order  of  events  was  to  be  as  follows:  1.  The  IV  crew  would  robotically  position  the  tip  of  the  boom  near  the  port  side  of  the  truss,  ready  for  the  EV  crew.  2.  The  EV  crew  would  install  the  WIF  Extender  and  a  foot  restraint  onto  the  tip  of  the  boom,  and  Parazynski  would  put  his  feet  into  the  foot  restraint.  
Purchased by unknown, nofirst nolast From: Scampersandbox (scampersandbox.tizrapublisher.com)
 
            




















































































































































































































































































































































































































































