5  SYSTEMS:  INTERNATIONAL  SPACE  STATION  PLANNING—A  ROADMAP  TO  GETTING  IT  ALL  DONE  CHAPTER  1  planners  to  evaluate  the  set  of  proposed  increment  requirements  for  feasibility  before  the  final  requirements  are  approved  while  allowing  planners  to  begin  developing  their  databases  of  activities.  Increment  planning,  performed  by  the  flight  control  planning  team,  is  broken  into  pre-increment  planning  and  execute  planning.  The  pre-increment  planning  phase  begins  1  year  prior  to  the  increment  start  and  ends  at  increment  start—3  weeks  (I-3  weeks).  As  described  in  detail  below,  the  primary  products  generated  during  this  phase  are  the  Increment  Overview,  On-orbit  Operations  Summary  (OOS),  and  the  Execute  Planning  Groundrules  and  Constraints  (Gr&C).  Three  weeks  prior  to  start  of  the  increment,  the  planners  begin  what  is  called  the  “execute”  phase.  The  primary  products  of  the  execute  phase  are  the  Monthly  Calendar,  Weekly  Lookahead  Plan  (WLP),  Short  Term  Plan  (STP),  Onboard  Short  Term  Plan  (OSTP),  and  Daily  Execute  Package.  Although  this  process  is  orderly,  significant  change  is  occurring  through  the  entire  process  as  ISS  Program  priorities  change.  Problems  such  as  broken  hardware  or  a  supply  mission  delay  are  the  main  drivers  for  these  changes.  Thus,  replanning  is  an  ongoing  process.  Increment  Planning  The  International  Execute  Planning  Team  (IEPT),  led  by  the  lead  operations  planner  resident  at  NASA  Johnson  Space  Center,  develops  the  pre-increment  products.  Planning  representatives  from  each  international  partner  (see  Introduction)—NASA,  Russia,  Europe,  and  Japan—comprise  the  IEPT.  The  Payloads  Operations  and  Integration  Center  organizes  research  in  the  United  States,  whereas  the  lead  mission  control  center  for  each  partner  coordinates  its  respective  research  activities.  The  IEPT  members  conduct  regular  conferences,  routinely  exchange  planning  data  according  to  a  predefined  schedule,  and  participate  in  two  face-to-face  meetings  for  pre-increment  planning  product  finalization.  During  the  execute  planning  phase,  IEPT  meetings  (telecons)  are  conducted  3  days  a  week  to  facilitate  WLP  and  STP  development  and  replanning.  A  key  task  during  pre-increment  planning  is  to  evaluate  the  feasibility  of  the  program  requirements.  At  this  stage  of  the  process,  planners  begin  translating  program  requirements  into  activities  and  assigning  these  activities  to  periods  of  time  during  the  increment  to  determine  whether  sufficient  resources  (e.g.,  crew  time)  are  available  and  whether  defined  activity  constraints  (e.g.,  microgravity  periods,  sufficient  day/night  cycles,  etc.)  can  be  satisfied.  Detailed  procedures  and  time  estimates  are  generally  not  available  at  this  stage  however,  the  operations  team  has  done  enough  analysis  to  have  a  reasonable  estimate  on  how  long  each  activity  will  take.  If  an  activity  is  particularly  complex,  the  operations  team  may  conduct  a  dry  run  in  the  mock-up  facility  to  improve  the  time  estimate.  Eventually,  as  the  time  of  executing  the  activity  gets  closer,  the  procedure  will  be  verified  and  the  final  time  estimate  will  be  available.  If  the  activity  has  been  performed  previously  or  is  suitably  similar  to  another  activity,  the  time  can  be  better  estimated.  However,  individual  crew  members  can  take  a  different  amount  of  time  to  perform  the  same  activity,  depending  on  background  or  previous  experience  in  space.  The  IEPT  develops  the  primary  products  of  this  phase—the  Increment  Overview,  OOS,  and  Gr&C—according  to  a  predefined  schedule  (Table  1).  Table  1.  Dates  are  referenced  to  the  start  of  the  increment  (I)  and  the  time.  I-12  indicates  12  months  before  the  start  of  the  increment.  Increment  Overview  Increment-Specific  Groundrules  &  Constraints  On-orbit  Summary  Draft:  I-12  months  Draft  development  occurs  ~I-8  through  I-4  months  Draft  development  occurs  ~I-8  through  I-4  months  Preliminary:  I-6  months  Preliminary:  I-4  months  Preliminary:  I-4  months  Final:  I-1  month  Final:  I-1  month  Final:  I-1  month  The  Increment  Overview  (Figure  1)  is  the  official  planning  document  until  1  month  prior  to  beginning  of  the  increment  when  the  final  OOS  provides  the  information  for  the  final  stages  of  planning.  The  document  contains  a  summary  of  key  increment  operations  such  as  spacewalks  and  illustrated  vehicle  traffic  to  and  from  the  ISS.  Vehicle  traffic  includes  the  Soyuz  flights  that  bring  the  new  crew  as  well  as  the  cargo  resupply  missions.  Further,  the  Increment  Overview  provides  estimates  of  crew  time  for  research  utilization.  For  example,  the  crew  might  have  an  expected  amount  of  30  to  40  crew  hours  available  in  one  week  for  experiments,  whereas  another  week  might  contain  a  spacewalk  and  may  only  have  5  to  10  hours  available.  The  OOS  as  shown  in  Figure  2  is  a  high-level  plan,  organized  by  day,  spanning  the  entire  increment  that  addresses  crew  time  usage  and  indicates  other  major  operations  (e.g.,  visiting  vehicle  arrivals/  departures,  EVAs,  significant  non-  crew  operations,  etc.).  The  intent  
Purchased by unknown, nofirst nolast From: Scampersandbox (scampersandbox.tizrapublisher.com)
 
            




















































































































































































































































































































































































































































